Focus: Water March 2007Western Australian water reform: the next stageIn brief: Senior Associate Robyn Glindemann and Lawyer Caitlin Westgarth report on the next stage of Western Australia's water reform program.
IntroductionOn 27 February 2007, Water Resources Minister John Kobelke released the Water Reform Implementation Committee's A Blueprint for Water Reform in Western Australia, Final Advice to the Western Australian Government (the Blueprint), the Government Response to A Blueprint for Water Reform in Western Australia, February 2007 (the Government Response) and Western Australia's Implementation Plan for the National Water Initiative, Final Draft February 2007 (the draft Implementation Plan). (All three documents are available at the Department of Water's website.) These three documents, together with the State Water Plan (which was released in draft form late last year), form the basis of the state's water reform program from now on, which will be guided by the National Water Initiative (NWI). The purpose of the reform program is to improve sustainable management and planning of the state's water resources and to increase security, certainty, productivity and efficiency of water for users and the environment. The Blueprint and the Government ResponseThe Blueprint sets out the Water Reform Implementation Committee's 72 recommendations to the State Government about how to develop and deliver water reform in Western Australia.1 The State Government has accepted the recommendations. The key proposals are the introduction of a new water entitlement system and statutory water management plans. The new water entitlement system will comprise:
Water access entitlements (and related works and site approvals) reflect the basic requirements of the NWI and therefore must be introduced in Western Australia. The current water licensing system will remain in place until a statutory water management plan is operative for a particular region, but may continue in force under a statutory plan where the resource system characteristics may preclude the establishment of a consumptive pool (and access entitlements), such as areas where water occurs in fractured aquifiers. This is particularly relevant in remote areas of the state where many mining operations are located. The statutory water management plans will set out the water entitlements for an area. These plans will also include information on an area's water resources, environmental water allocations, how risk is to be allocated if the consumptive pool changes, the applicable local water trading rules, how over-allocated systems are to be dealt with and issues specific to that area. These plans will be legally binding and cannot be appealed once they are completed. They will be reviewed at least once every 10 years. Given the importance of the statutory water management plans, it is crucial that stakeholders are actively involved in the consultation process during preparation of these plans. The statutory water management plans will be prepared on a priority basis starting with those areas which are near, or at, full allocation. The current top four priority areas are Gnangara groundwater mound, the South-West groundwater areas, the Collie surface water and groundwater areas, and the Pilbara region surface water and groundwater areas. Other recommended reforms include increasing the metering of water to improve water-use efficiency and obtaining information to facilitate allocations and trading. For existing water licence holders, allocations equal to, or more than, 50 megalitres (ML) a year will be metered.2 Current allocations less than 50ML a year may be metered in situations where the statutory water management plan requires it, including where:
All new licences will be metered despite the volume and location. A licence administration fee for all Section 5C licences and new licence
applications under the current Rights in Water and Irrigation Act 1914
(WA) to take water is intended to be imposed from July 2007
in accordance with the following schedule of fees:
An initial and non-refundable fee of $200 will also be imposed on applicants for new licences to take water or to construct or alter a well and new applications for permits to obstruct or interfere with river beds and banks. Water resource management fees are likely to be introduced following the establishment of a national approach to recovering these costs, the completion of statutory water management plans and the creation of longer term secure water access entitlements. Draft NWI Implementation PlanAs with the other states and territories, Western Australia is required to prepare an Implementation Plan outlining how and when it intends to deliver its obligations under the NWI. The recently released draft Implementation Plan has drawn on the consultation undertaken for the Blueprint and the State Water Plan. The majority of the systems and mechanisms required to deliver the water reforms will be developed over the next two years. These will include building a register for water access entitlements, creating a water trading register and implementing metering systems (starting in the areas where statutory water management plans are a priority). New legislation is anticipated by the end of 2008 to consolidate existing water legislation and underpin the proposed water reforms, such as the statutory water management plans. This legislation will repeal and replace the Rights in Water and Irrigation Act and a range of other water-related legislation. The final Implementation Plan is due in April 2007 with the final State Water Plan. We will continue to monitor the water reform program and report on further proposed reforms as they are released. Footnotes
For further information, please contact:
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
![]() |
||||